The Rhode Island Department of Transportation (RIDOT) announced its schedule for paving work this fall that will resurface “badly worn” portions of Hartford Avenue in Johnston and Scituate.

“Work on the paving will take place during both daytime and evening hours. Generally, work on portions of these roads that pass through residential areas will be done in the daytime. Those along busy commercial corridors or where traffic is heavy, especially west of I-295, will be done during the nighttime,” said the RIDOT in their press release.

RIDOT adds that work on each segment will begin with a period of “pavement milling, during which motorists should expect a rough driving surface and raised structures such as utility covers and drainage grates. Travel delays are possible.”

GET THE LATEST BREAKING NEWS HERE -- SIGN UP FOR GOLOCAL FREE DAILY EBLAST

The schedule this fall includes:

Hartford Avenue (Route 6A) from Killingly Street to Atwood Avenue (Route 5): Begins the week of September 17 and continues until late October. This project also included the installation of Americans with Disabilities Act-complaint wheelchair ramps at various locations throughout the 1.7-mile construction zone.

Hartford Avenue (Route 6) from I-295 to Danielson Pike: Begins the week of September 17 and continues until early October. This project included limited sidewalk replacement along its 1.5-mile length, and the reconstruction of the intersection of Hartford Avenue and Reservoir Avenue in Johnston.

Hartford Pike (Route 6) from Danielson Pike to Route 101: Begins late September/early October and continues until late October. This segment is 1.8 miles long in Scituate.